How the job went
Work started on an excavated red-earth site, with footings and short stumps cast first, then a grid of ground beams formed in timber, cast and backfilled. The ground slab was reinforced and poured, the columns were formed and cast, and the first-floor slab, stairs and roof slab followed on scaffolding. The finished two-storey building was photographed in March 2020.